Total feature list:

  • Model 2 Tooth
    • Loading in the references and scaling them (1hr)
    • Modeling based on reference (2-6hrs)
    • adding the material to the model (2hrs)
    • render the model (2hrs)
    • export the model (1hr)
    • Get feed back (1hr)
    • Implement feed back (2hr)
    • Send to 3D printer for test printing
  • Work on 3nd model ( 1 week)Loading in the model into Blender (1hr)
    • Sculpting the details into the pliers (1-4 hrs)
    • Taking model 1’s color and shading and applying it to this mode (1-2hrs)
    • render the model (1-6 hrs)
    • Export the model (1-2hrs)
    • Get feed back (1hr)
    • Implement feed back (3hr)
  • Testing out the mobility of the models (3hrs)
  • Import surgical models into the 3D environment (2-6hrs)
  • Work on 3nd model ( 1 week)
    • Loading in the model into Blender (1hr)
    • Sculpting the details into the pliers (1-4 hrs)
    • Taking model 1’s color and shading and applying it to this mode (1-2hrs)
    • render the model (1-6 hrs)
    • Export the model (1-2hrs)
    • Get feed back (1hr)
    • Implement feed back (3hr)
  • Model 4 Tooth
    • Loading in the references and scaling them (1hr)
    • Modeling based on reference (2-6hrs)
    • adding the material to the model (2hrs)
    • render the model (2hrs)
    • export the model (1hr)
    • Get feed back (1hr)
    • Implement feed back (2hr)
  • Model 1 Surgical pliers
    • Loading in the model into Blender (1hr)
    • Sculpting the details into the pliers (1-4 hrs)
    • Coloring (1-2 hr)
    • Shading (1-6 hrs)
    • Adding metallic shading (1-4hrs)
    • render the model (1-6 hrs)
    • Export the model (1-2hrs)
    • Get feed back (1hr)
    • Implement feed back (3hr)
  • Research on material that can be used for 3D printing (2hrs a day)
  • Contact other partners about ways of printing (1-4hrs week)

Work Plan for iteration 1:

  • Model 2 Tooth Loading in the references and scaling them (1hr)
    • Modeling based on reference (2-6hrs)
    • adding the material to the model (2hrs)
    • render the model (2hrs)
    • export the model (1hr)
    • Get feed back (1hr)
    • Implement feed back (2hr)
    • Send to 3D printer for test printing
  • Import surgical models into the 3D environment (2-6hrs)
  • Contact other partners about ways of printing (1-4hrs week)
  • Work on adding shaders and material to other 3D models

The colors of the text represent how important the task are to do, red means they are the most important thing that needs to be done in this iteration. Yellow means that they are important but can be worked on when waiting on things that are red. Purple means things that are not important now but will be part of future iteration but can be pushed off for now. Green means that it has been completed in past iterations.